Steel Dynamics
Location: Columbus, Mississippi
ABC was called in to create a 20’ x 20’ x 4’ deep pit in an existing 6’ deep concrete slab for new equipment to be installed. ABC cut a perimeter trench and broke it out to allow the 400 sq ft area to be wrapped with a diamond wire and cut the 20’ x 20’ area at 2’ below top of slab. Our team then repeated the same procedure again to complete the 4’ deep pit. ABC also cut multiple large concrete pedestals off flush with the plant floor for removal. The Job was completed ahead of schedule with ABC working multiple shifts around the clock.